KVDT Phase 2 Project Will Be Resumed With Savings of Over RM700 Million
Bernama, Photo Credit to KLIA2 Info
clock 10-07-2019
hit 223

The 110-kilometre Klang Valley Double Track (KVDT) Phase 2 project will be revived with a cost reduction of over RM700 million, said the Transport Ministry, Anthony Loke Siew Fook. He said that the Cabinet on July 5 decided that the project will be resumed by Dhaya Maju LTAT Sdn Bhd with a new contract costing RM4.475 billion, which is a reduction of 15% from the original cost.

“(The cost reduction) does not reduce the critical scope set by the government,” he said during the Ministers’ Question time in the Dewan Rakyat on 9 July 2019.

He was responding to a question from Ahmad Fahmi Mohamed Fadzil (PH-Lembah Pantai) on the current status of KVDT Phase 1 and Phase 2 project. He said the implementation of the KVDT Phase 2 project was set for seven years.


Why re-award the contract to the company who allegedly had poor performance executing KVDT Phase 1 project?


Responding to an additional question by Ahmad Fahmi, on why the government re-awarded the contract to the company when it allegedly had poor performance while executing KVDT Phase 1 project, Loke said this was because the government would face legal implications if it did not resume the contract.

“If we do not resume the contract with the company, the government will face legal implications in which the company can sue the government and claim about RM2.5 billion in compensation,” he said.


Status of KVDT Phase 1


With regard to the KVDT Phase 1 project, Loke said the progress status of the project as at 30 June 2019 had reached 80.33%.

Meanwhile, Loke agreed that the implementation of the project would affect the service of KTM Komuter and the Electric Train Services (ETS) trains in terms of the frequencies and travel time.

“However, the government through the Land Public Transport Agency (APAD) will constantly monitor the performance of public transport services in Malaysia to ensure that the responsible operator would follow the set standards,” he said.




WHAT DO YOU FEEL ABOUT THIS?

0
LOVE
0
HAPPY
0
SURPRISED
0
SAD
1
ANGRY


COMMENTS
Use a Facebook account to add a comment, subject to Facebook's Terms of Service and Privacy Policy. Your Facebook name, photo & other personal information you make public on Facebook will appear with your comment.

SIGN UP NEWSLETTER

logo
Monthly Column
The staple of your property-related materials. It's all about being ahead of the game and with The Column, you get carefully selected information that will keep you informed and running with the pack. The best news, articles and properties on the market from the Property Hunter portal, conveniently wrapped and ready, just for you.

logo
Weekly Window
Your weekly dose of what's hot and what's not in property. The window is your view into the realm of real estate in Malaysia, curated from our portal based on the most popular pieces over the week. For those who just can't get enough, this is for you. Ain't nobody got time for dailies anymore, weekly is the new daily.